Independent Engineering Report
Detailed IE reports for developers, owners and financiers evaluating energy storage technologies and projects for debt, equity investment and M&A.
Bankable Review for Financing, Investment and M&A
Fractal Energy Storage Consultants provides detailed Independent Engineering (IE) Reports to support developers, owners and financiers in evaluating technologies and projects for debt, equity investment and M&A.
Contact Fractal for a detailed scope of work and report organization specific to your project or portfolio and sponsor requirements.
Report Scope
Each report is organized around the project and the sponsor’s requirements. A typical scope covers the following areas.
Technical Evaluation
- Equipment provider and EPC experience, track record, bankability, point of origin and known performance issues
- Division of responsibility (DOR) across suppliers, integrator, MV/HV EPC, OE and owner; gap identification
- Design adequacy for the intended application: C-rate, chemistry, duty cycle and voltage range
- Plant sizing to deliver required power, energy and PF at the POI or POM
- BESS and BOP components, cross-compatibility, SLD and layout
- Unit, site and master plant controls; BMS functionality, including balancing and power limiting
- EMS/SCADA/MPC bankability and track record
- Degradation management: initial sizing vs. augmentation
- Auxiliary loads, metering locations, network ownership
- Proposed design vs. commercial and technical specifications; suitability of test plans
- Code and AHJ compliance; spare parts suitability
Commercial Provisions
- Agreement inventory, counterparties and construct (exhibits, definitions, order of precedence)
- Equipment supply agreements, EMS/PPC, MPC, SLA, EPC, offtake, AMA and O&M
- Availability and performance guarantees: applicable equipment, POM vs. POI, measurement period, grace periods, maintenance allowance and auxiliary load treatment
- SAT and annual test plans, re-test rights and impacts on usable power and energy
- Liquidated damages: key definitions, accrual, individual or aggregate caps, bonuses and buydowns
- Equipment warranties (warehouse and operational): scope, terms, limitations, exclusions and degradation curves
- Payment milestones and contingencies; spare parts and shipping delays
- Back-to-back coverage gaps, imposed software and domestic content methodology
- Transferability, termination, default, dispute resolution and force majeure
Financial Model Review
- Battery characteristics: chemistry, C-rate, cycle and calendar life, efficiency and efficiency degradation, auxiliary load, installed vs. usable power and energy, duty cycle, resting and average SOC
- Duty cycle simulation and validation against technology selection and sizing
- BOP characteristics, scope and efficiency curves
- CAPEX and OPEX benchmarking and reasonableness of project costs
- Revenue forecasts, price fundamentals and third-party dispatch assumptions
- Asset registration and technical requirements for wholesale market participation
- Federal, state and local incentives, adders and subsidies
- P50 vs. P90/P95 generation analysis, if applicable
- End-of-life considerations
- Working capital, major maintenance, O&M, spare parts inventory and operating budget
Grid Connection and Electrical Review
- Interconnection application inputs and status; definition of material modification
- Allowable export capacity, power factor and reactive capability requirements at the POI
- Charging requirements and restrictions, including self-charging from renewables and transmission service
- Load assessment studies required before charging is permitted
- Operating range and SOC requirements for frequency response; MPC or equivalent requirements
- Metering, SCADA, telemetry, communications and data reporting requirements
- Control and protection systems for charging and discharging
- System disturbance response, stability modeling and studies
- Pre-COD testing requirements and commissioning performance metrics
- Grid code compliance and provisions for augmentation, replacement or expansion
Site, Safety and Delivery
The report also covers permitting, site conditions, fire safety, operations, schedule and commissioning.
Site Conditions and Environmental
- Topography, site maps and usable vs. allowable space for laydown, access, construction and augmentation
- Climate, humidity, temperature extremes, tropical storm and tornado risk; corrosion risks (icing, dust, sand)
- Subsurface conditions, foundations and equipment suitability for site conditions
- Site access and transport infrastructure (ports, roads, vehicles); proximity to residential areas
- Applicable laws, regulations, codes and standards
- Environmental restrictions; status of studies
Permits and Licenses
- Permitting DOR and status
- Land use, building and environmental permits
- State contractor license and other required permits
Fire Safety
- Local and state requirements and code versions
- Water supply, container spacing and alarm locations
- Hazard Mitigation Analysis (HMA), Emergency Response Plan (ERP), decommissioning plan and performance tests
Project Schedule
- Schedule suitability to achieve COD, including long-lead items, contingencies and weather delays
- Payment and LD milestones; environmental permit limitations
- Market participant telemetry and testing dates
O&M Program
- Preventive, corrective and primary maintenance plans and monitoring program
- Staffing, start-up, training, labor management and key staff qualifications
- Spare parts warehousing and shortage risk
- Suitability of the O&M program and adequacy of the availability guarantee
Commissioning and Testing
- Commissioning DOR and alignment with the project schedule
- Commissioning spare parts inventory
- Test plans (cold, hot, unit-level, site acceptance, annual performance) vs. revenue and offtake requirements